Current Projects

Sports Complex Walkway and ADA Parking Improvements - Complete
Sports Complex Irrigation System Improvements - Complete
Sports Complex Tree Installation Project - Pending. Working with TAC to finalize tree locations. Irrigation still needs to be installed at each tree site before planting can begin.


About the Camp Verde Sports Complex

Overview of the History of the Sports Complex

Late 90’s - Early 2000’s

Before acquiring the land where the Sports Complex now stands, the Town had plans to build the park on the school property across SR260. Funds were invested in developing a concept plan with an architect, and a copy of this plan is available in the Public Works Department. This history is important because it demonstrates the Town's long-standing commitment to establishing a large community park, a vision that dates back to the 1990s.

The Town of Camp Verde was awarded $2.5 million in a Land and Water Conservation Fund Grant (LWCF) for construction at the Camp Verde Sports Complex. The LWCF State & Local Assistance Program provides matching grants for local and state park projects outside national park boundaries. LWCF grants are locally determined and competed for at the state level through a process designed and managed by Arizona State Parks and Trails.

Camp Verde Economic Development staff worked with Public Works and Parks & Recreation to submit the original grant request in the spring of 2020. The State parks Board approved the grant in October 2020, however, due to COVID the final award was postponed until September of 2021. The grant required matching funds from the Town so the decision was made in the fall of 2020 to place much of the construction on hold in order to conserve the available Town funds to meet the match. It was hoped that the grant decision would be made before the start of 2021 but that turned out to not be the case.

During the waiting period, Town Council approved funding for time sensitive pieces of the project including the permanent underground connection for the reclaimed water from the Wastewater Treatment plant, parking lot improvements, and items such as bleachers, goal posts, and scoreboards that would allow play on the Soccer/Football fields in the fall 2020 even if complications with the grant delayed the project longer. Also during this period, Public Works began engaging with Arizona Department of Transportation regarding plans for the expanded access to the park off Hwy 260.

In September 2021 Public Works began working with Tierra Verde Builders to resume the large scale construction on the project. The primary goals were to have the soccer and football fields ready to be used late that fall and the baseball/softball fields ready for play the following spring. We were working with a local architect to complete the design work for the restroom/concession building with the finish date still undetermined.

In February 2023 major milestones were achieved. The sanitary sewer system was completed in preparation for the future concession/restroom building. Tierra Verde Builders installed the field lighting systems for the soccer/football fields and baseball fields. They were also able to complete the chain-link fencing around the baseball fields. Within the next few months additional improvements were completed, including the dugouts, baseball infields, football goal posts, flag poles, the concrete curbing for the entry walkway, and storm drain system.

Along the way the park has presented numerous challenges to overcome. One of these challenges included how the Town planned to irrigate the fields. We planned to use reclaimed water on the fields but to allow the public on the fields while irrigating with reclaimed water, an amendment to the Town’s Aquifer Protection Permit was required by the Arizona Department of Environmental Quality. This was an important document that addressed the safety aspect of using something other than potable water to use for irrigation. At that point the wastewater treatment facility was producing A+ water for over a year without a problem. This water is deemed the highest quality recycled water and is generally safe for human exposure.

The sports complex is now open and ready for use. Over 65,000 people have visited the park in 2024 alone. While residents and visitors can enjoy the amenities currently available, there are still significant projects the Town plans to complete. The most significant of these include the addition of a concession/restroom facility in the promenade directly adjacent to the baseball fields. We anticipate this amenity to be complete in April 2025. With the arrival of the concession/restroom building we will finally be able to install the concrete walkway from the parking lot up to the promenade area. This work will be completed immediately after the concession building is complete.

Other future projects include the installation of a maintenance building and pickleball courts. The maintenance building will house the equipment and supplies necessary to maintain the sports complex. This building would be situated along the south side of Champion Trail across from the parking lot. Future pickleball courts have a home at the sports complex immediately south of the south baseball field. Lighting for these courts has already been installed. We will also be installing shade trees throughout the park.

Overview of the History of the Sports Complex

Late 90’s - Early 2000’s

Before acquiring the land where the Sports Complex now stands, the Town had plans to build the park on the school property across SR260. Funds were invested in developing a concept plan with an architect, and a copy of this plan is available in the Public Works Department. This history is important because it demonstrates the Town's long-standing commitment to establishing a large community park, a vision that dates back to the 1990s.

The Town of Camp Verde was awarded $2.5 million in a Land and Water Conservation Fund Grant (LWCF) for construction at the Camp Verde Sports Complex. The LWCF State & Local Assistance Program provides matching grants for local and state park projects outside national park boundaries. LWCF grants are locally determined and competed for at the state level through a process designed and managed by Arizona State Parks and Trails.

Camp Verde Economic Development staff worked with Public Works and Parks & Recreation to submit the original grant request in the spring of 2020. The State parks Board approved the grant in October 2020, however, due to COVID the final award was postponed until September of 2021. The grant required matching funds from the Town so the decision was made in the fall of 2020 to place much of the construction on hold in order to conserve the available Town funds to meet the match. It was hoped that the grant decision would be made before the start of 2021 but that turned out to not be the case.

During the waiting period, Town Council approved funding for time sensitive pieces of the project including the permanent underground connection for the reclaimed water from the Wastewater Treatment plant, parking lot improvements, and items such as bleachers, goal posts, and scoreboards that would allow play on the Soccer/Football fields in the fall 2020 even if complications with the grant delayed the project longer. Also during this period, Public Works began engaging with Arizona Department of Transportation regarding plans for the expanded access to the park off Hwy 260.

In September 2021 Public Works began working with Tierra Verde Builders to resume the large scale construction on the project. The primary goals were to have the soccer and football fields ready to be used late that fall and the baseball/softball fields ready for play the following spring. We were working with a local architect to complete the design work for the restroom/concession building with the finish date still undetermined.

In February 2023 major milestones were achieved. The sanitary sewer system was completed in preparation for the future concession/restroom building. Tierra Verde Builders installed the field lighting systems for the soccer/football fields and baseball fields. They were also able to complete the chain-link fencing around the baseball fields. Within the next few months additional improvements were completed, including the dugouts, baseball infields, football goal posts, flag poles, the concrete curbing for the entry walkway, and storm drain system.

Along the way the park has presented numerous challenges to overcome. One of these challenges included how the Town planned to irrigate the fields. We planned to use reclaimed water on the fields but to allow the public on the fields while irrigating with reclaimed water, an amendment to the Town’s Aquifer Protection Permit was required by the Arizona Department of Environmental Quality. This was an important document that addressed the safety aspect of using something other than potable water to use for irrigation. At that point the wastewater treatment facility was producing A+ water for over a year without a problem. This water is deemed the highest quality recycled water and is generally safe for human exposure.

The sports complex is now open and ready for use. Over 65,000 people have visited the park in 2024 alone. While residents and visitors can enjoy the amenities currently available, there are still significant projects the Town plans to complete. The most significant of these include the addition of a concession/restroom facility in the promenade directly adjacent to the baseball fields. We anticipate this amenity to be complete in April 2025. With the arrival of the concession/restroom building we will finally be able to install the concrete walkway from the parking lot up to the promenade area. This work will be completed immediately after the concession building is complete.

Other future projects include the installation of a maintenance building and pickleball courts. The maintenance building will house the equipment and supplies necessary to maintain the sports complex. This building would be situated along the south side of Champion Trail across from the parking lot. Future pickleball courts have a home at the sports complex immediately south of the south baseball field. Lighting for these courts has already been installed. We will also be installing shade trees throughout the park.

Overview of the History of the Sports Complex

Late 90’s - Early 2000’s

Before acquiring the land where the Sports Complex now stands, the Town had plans to build the park on the school property across SR260. Funds were invested in developing a concept plan with an architect, and a copy of this plan is available in the Public Works Department. This history is important because it demonstrates the Town's long-standing commitment to establishing a large community park, a vision that dates back to the 1990s.

The Town of Camp Verde was awarded $2.5 million in a Land and Water Conservation Fund Grant (LWCF) for construction at the Camp Verde Sports Complex. The LWCF State & Local Assistance Program provides matching grants for local and state park projects outside national park boundaries. LWCF grants are locally determined and competed for at the state level through a process designed and managed by Arizona State Parks and Trails.

Camp Verde Economic Development staff worked with Public Works and Parks & Recreation to submit the original grant request in the spring of 2020. The State parks Board approved the grant in October 2020, however, due to COVID the final award was postponed until September of 2021. The grant required matching funds from the Town so the decision was made in the fall of 2020 to place much of the construction on hold in order to conserve the available Town funds to meet the match. It was hoped that the grant decision would be made before the start of 2021 but that turned out to not be the case.

During the waiting period, Town Council approved funding for time sensitive pieces of the project including the permanent underground connection for the reclaimed water from the Wastewater Treatment plant, parking lot improvements, and items such as bleachers, goal posts, and scoreboards that would allow play on the Soccer/Football fields in the fall 2020 even if complications with the grant delayed the project longer. Also during this period, Public Works began engaging with Arizona Department of Transportation regarding plans for the expanded access to the park off Hwy 260.

In September 2021 Public Works began working with Tierra Verde Builders to resume the large scale construction on the project. The primary goals were to have the soccer and football fields ready to be used late that fall and the baseball/softball fields ready for play the following spring. We were working with a local architect to complete the design work for the restroom/concession building with the finish date still undetermined.

In February 2023 major milestones were achieved. The sanitary sewer system was completed in preparation for the future concession/restroom building. Tierra Verde Builders installed the field lighting systems for the soccer/football fields and baseball fields. They were also able to complete the chain-link fencing around the baseball fields. Within the next few months additional improvements were completed, including the dugouts, baseball infields, football goal posts, flag poles, the concrete curbing for the entry walkway, and storm drain system.

Along the way the park has presented numerous challenges to overcome. One of these challenges included how the Town planned to irrigate the fields. We planned to use reclaimed water on the fields but to allow the public on the fields while irrigating with reclaimed water, an amendment to the Town’s Aquifer Protection Permit was required by the Arizona Department of Environmental Quality. This was an important document that addressed the safety aspect of using something other than potable water to use for irrigation. At that point the wastewater treatment facility was producing A+ water for over a year without a problem. This water is deemed the highest quality recycled water and is generally safe for human exposure.

The sports complex is now open and ready for use. Over 65,000 people have visited the park in 2024 alone. While residents and visitors can enjoy the amenities currently available, there are still significant projects the Town plans to complete. The most significant of these include the addition of a concession/restroom facility in the promenade directly adjacent to the baseball fields. We anticipate this amenity to be complete in April 2025. With the arrival of the concession/restroom building we will finally be able to install the concrete walkway from the parking lot up to the promenade area. This work will be completed immediately after the concession building is complete.

Other future projects include the installation of a maintenance building and pickleball courts. The maintenance building will house the equipment and supplies necessary to maintain the sports complex. This building would be situated along the south side of Champion Trail across from the parking lot. Future pickleball courts have a home at the sports complex immediately south of the south baseball field. Lighting for these courts has already been installed. We will also be installing shade trees throughout the park.

Basic Timeline of Progress on the Sports Complex

2024

  • April 2024: The erosion control riprap was installed, the irrigation rain sensor, control panel, and coaches’ switches were set up, and the scoreboards were completed and became operational.

2023

  • January: Conduit completed
  • January-February: APS hookup, completion of baseball fields, scoreboards and football field goals installed
  • February: the sanitary sewer system completed, the MUSCO lighting on the baseball and soccer fields installed, the chain link fencing around the baseball fields completed
  • June: The storm drain system completed, the concrete curb along the entryway completed, the football goal posts installed, the sliding gates on the baseball field fencing installed, the baseball dugouts completed, the baseball field infields completed and bases installed, the flag poles are installed

2022 Approval from AZ State Parks to Begin Ground Disturbances

  • February: Monitoring Plan submitted for review by State Historic Preservation Officer, State Parks, and Tribes. 
  • April 11: Approval to begin ground disturbance from AZ State Parks (LWCF)
  • May: Contractor installed part of the chain link fencing for the baseball fields, Streets Division installed temporary fencing, installed concrete blocks, and port-a potties delivered
  • May: Streets built lower loop trail 
  • June 6: Soft Opening for multi-use field only  
  • August: Light poles delivered and first Soccer Tournament scheduled
  • October: Lighting installed
  • November: Dugouts completed
  • December: Backstops completed

2021 Archeological Clearance & Ground Disturbance

  • August-September: LWCF grant funding available via Waiver - allowable projects include restrooms, maintenance facility, concession stand, irrigation, water supply, fishing reservoir, APS service to the site, fiber optic line, potable water well, wastewater lift station, field lighting, bleachers, parking lot, entrance, and central plaza.
  • September-December: Tierra Verde Builders completed work with Stored Materials.
  • October: Hired Archeologist Lynn Neal to prepare the Monitoring Plan and monitor excavation work at the CVSC.

2020-2021 September 2020 - September 2021: Project on hold waiting for LWCF Funding

2020 Land and Water Conservation Fund Grant Opportunities and Delays

  • February: Phase 1B, 2nd Bid, Awarded to Tierra Verde Builders.
  • August-September: Project placed on hold to await funding from State Parks Land and Water Conservation Fund (LWCF) Grant. Funding was to be available in October-November 2020
  • September: Town awarded a $5 million dollar grant ($2.5M in grant funds with $2.5M match required) through LWCF

2019 Phase 1B Bidding and Project Scoping

  • April: Phase 1B, 1st Bid (19-133) advertised
  • May-June: Bids received and rejected due to insufficient funding
  • June-November: Phase 1B, redesign/reduction of project scope to fit budget
  • November: Phase 1B, 2nd Bid (19-139) advertised.

December: ERC Completes Construction on Phase 1A

2018 Phase 1B Design Begins

  • January-March: Sports Complex Phase 1A (18-125) advertised for bid and awarded to Earth Resources Corporation (ERC) in March 2018
  • April: Awarded Kimley-Horn Phase 1B design
  • June: Obtained a 2nd USFS Permit for Utilities & Access across a section of USFS Land for the Sports Complex Utilities to cross over to the WWTP. This required hiring an Archeologist to clear the site and a Surveyor to prepare the dedication survey. 
  • December: Perimeter trail construction completed. Trail expanded to 10’ wide and path upgraded to a stabilized aggregate base and added connector trail to McCraken with additional $25,226 from Park construction funds. Access road now paved and parking lot surface now millings.

2017 

  • January: design awarded to Kimley-Horn. Design completed in November 2017.
  • April: Entrance Road Design added to Kimley-Horn’s design contract.
  • December: the Town secured a loan/bond for $7,031,768.55 ($6,770,903.58 after overhead/insurance costs).

2016 Grading, Drainage and Infrastructure Phase 1A Begins

  • Parks & Recreation (P&R) applied for $78,248 Federal Recreation Trails Program (RTP) Grant through Arizona State Parks - 1.6 mile 4’ wide dirt Perimeter Loop trail around the vacant Sports Complex land w/dirt access road and parking lot.
  • Grant required a $25,331 Town match, mostly in-kind.
  • Council decides to begin work on Sports Complex, Fall of 2016
  • P&R works on updating RBF Consulting park concept plan
  • December: updated park concept plan presented to Council.
  • Selected Kimley-Horn, via “On call Services” list interview process in 2016, to design Phase 1A; Grading, Drainage, & Infrastructure Plans.

2014

  • USFS issued a Public Road Easement in 2014 to the Town for the Sports Complex Entry Road.

2012

  • Town hired an archeologist and surveyor to prepare the dedication survey of the legal boundary for the easement into the property.

2008

  • After completing the Master Study the impacts of the recession caused the Sports Complex to be placed on hold.

March

  • Town purchased 118.69 acres of USDA Forest Service Land for 2.4 million. 
  • RBF Consulting produced a Master Concept plan for the park.
  • Plan approved by Council 11/12/2008 - Layout only, no construction documents- Vision meeting w/ Council, 3 Public Workshops and joint Council & YAN Tribal Council workshop

Planned Expenditures 

  •  Planned Sports Complex Projects
  • FY25 Planned Sports Complex Expenditures (3.25.2025)
  • FY25 Planned Sports Complex Expenditures (11.25.2024)
  • FY25 Planned Sports Complex Expenditures Graph (11.25.2024)
  • FY25 Planned Sports Complex Projects Financials (9.6.2024)
  • FY25 Planned Sports Complex Expenditures Graph (9.6.2024)

Current Capital Improvement Projects in Progress at the Sports Complex 

Waterline Installation

This project will install a 6” potable watermain along Champion Trail to supply the new concession stand/restroom facility with potable water.

Concession Stand/Restrooms

The sports complex will finally be receiving its concession stand/restroom building. The Town has contracted with CorWorth Restroom Facilities to construct and install a prefabricated building on the existing promenade just west of the existing baseball fields.

Concession Stand/Restrooms Electrical Service

This project will provide the electrical supply to the proposed concession stand/restroom building.  While there is conduit currently in the ground for this service, staff will need to work with a licensed electrician to install the necessary wiring. 

Lift Station

It will be necessary to dispose of sanitary waste generated from the new restroom building.  This project will construct a sanitary sewer lift station to pump the solid waste up to the wastewater treatment facility for processing.  The project includes the construction of the wet well and installation of all of the pumps, control panel, and other infrastructure required to operate the wet well. 

Force Main

This project is a natural extension of the sports complex wet well project. It will provide the piping necessary for the solid waste to reach the sewer treatment facility. Much of the piping is currently in the ground. There is a small portion of piping that must be installed between the park and wastewater treatment facility to connect it to the facility.  

Irrigation Line Installation

Irrigation is a key part of the infrastructure of the sports complex. With this project the Town will install a new, larger reclaimed water storage pond at the southwest corner of the treatment facility.  New pumps will feed the irrigation system at the sports complex to provide irrigation to all of the turf areas in the park. This system will also provide water to the numerous shade trees due to be planted. 

Shade Trees Installation

Once sufficient irrigation is available the Town will purchase and install numerous shade trees around the park. Much like the park itself, these trees will be small at first, but will mature into staples of the park capable of providing ample shade for visitors.

Summary of the AZ State Parks Land and Water Conservation Fund Grant 

  • Awarded September 2021
  • $2.5 million matching grant for total $5 million
  • Federal grant administered by the AZ. State parks Land and Water Conservation Fund
  • Allowable construction areas:
    • Main fields
    • Ball fields
    • Fencing
    • Dugouts
    • Backstops
    • Field goal (football)
    • Scoreboards
    • Restroom facility & concession stand
    • Irrigation
    • Water supply
    • Fishing reservoir
    • APS service to the site and fiber optic line
    • Well for potable water
    • Maintenance facility
    • Waste water lift station
    • Field lighting
    • Bleachers
    • Parking lot
    • Central plaza

Summary of the AZ State Parks Land and Water Conservation Fund Grant 

  • Awarded September 2021
  • $2.5 million matching grant for total $5 million
  • Federal grant administered by the AZ. State parks Land and Water Conservation Fund
  • Allowable construction areas:
    • Main fields
    • Ball fields
    • Fencing
    • Dugouts
    • Backstops
    • Field goal (football)
    • Scoreboards
    • Restroom facility & concession stand
    • Irrigation
    • Water supply
    • Fishing reservoir
    • APS service to the site and fiber optic line
    • Well for potable water
    • Maintenance facility
    • Waste water lift station
    • Field lighting
    • Bleachers
    • Parking lot
    • Central plaza

Grant Funds for Special Projects

Grant funds are obtained and put into action through targeted writing, hard work, and careful administration by Town staff. The process of implementing grant-funded projects often requires collaboration and across divisions and coordination of volunteer hours. 

2017: Perimeter Loop Trail - Parks & Recreation staff received $78,000 from the Recreation and Trails Program under the AZ State Parks & Trails to build the 1.6-mile walking trail around the Sports Complex. The Town Council supplemented the grant and upgraded to a 10 ft wide trail constructed of stabilized aggregate base. See details here. 

2021: Park Benches - Parks & Recreation staff received $6,700 from an AARP Community Challenge Grant to purchase and install 8 park benches on the walking trail around the Sports Complex. See details here.

2022: Canopy of Trees - Parks & Recreation staff received $10,000 AZ Public Service company to purchase and plant trees at the Sports Complex. This project will commence when irrigation is in place.

2024: Hauser & Hauser Farms Donation - Parks & Recreation received $4,350 in donations for trees at the Sports Complex. This project will commence when irrigation is in place.



FAQs

The community can help and/or contribute to the Sports Complex by reaching out to Town of Camp Verde Parks and Recreation at 395 S Main Street, Camp Verde AZ or (928) 554-0820 or by contacting the Camp Verde Recreation Association. Both organizations welcome community involvement and can provide information on volunteer opportunities, donation options, and ways to support ongoing and future projects at the complex.

When additional funding is available, we plan to enhance the unprogrammed spaces by incorporating requested features such as

  • a dog park
  • sand volleyball courts
  • a pump track for diverse recreational activities

Other ideas for potential additions include

  • mountain biking trails
  • playgrounds
  • an outdoor event space
  • an RV dump station
  • shaded ramadas to improve visitor comfort
  • planting more trees to enhance the park's natural beauty

The project has experienced delays due to a combination of factors, including the postponement of the grant award until September 2021 due to COVID-19, and the need to conserve Town funds for the required match. While waiting for the final grant approval, the Town Council prioritized essential components such as waterline connections, sewer, concession/restrooms, and ADA main entrance walkway to ensure forward progress.